November 25, 2024. Monday Momentum. Progress. Perform. Protect. Page 1.  New this week...KVR-3 has been working with utility providers on plans to relocate utility lines that run between the high school and the tech center, in preparation for construction and future growth. The location of the hallway connecting KATC and KHS has been determined. Architects continue to develop the design for the connector. Construction to begin in the summer of ‘25. Connector hallway will provide protection for students as they pass between the two buildings. It will reduce outsider access to the buildings during passing periods.

November 25, 2024. Monday Momentum. Progress. Perform. Protect. Page 2. Current vs. coming soon...Photo of: KHS and KATC current and coming soon.Kirksville R-3 has been working with utility providers on plans and logistics for relocating utility lines that run between Kirksville High School and the Kirksville Area Technical Center. This process is detailed and crucial for both the construction phase and long-term planning for future growth.

Architects have determined the best location for the hallway that will connect KHS and KATC. They continue to develop its design. The connector is part of the construction project planned to begin in the summer of 2025.

The connector hallway will further secure both KATC and KHS buildings. It will provide protection for students as they move between the two buildings, while also reducing outsider access during passing periods.